Our first phase is off to a good start with installation of new generator, 10,000 gallon diesel tank, water lines, fuel lines, and finish concrete pads for new equipment… all while airport fueling loads take place. We are working through the challenge of a tight site and limited space for material laydown but the weather is grand and we are working safe and staying healthy while building this essential facility for the airport.